Render Billing as PDF, Schedule of Values

Sheet Billing, Holiday Lighting, Install

Raw Install Labor, 1446.23
MOB, 542.34
Raw Install Labor, 15.00
Swagging - Canopy Lights - 36", 204.87
Holiday Lighting Install
Total 2208.44 2208.44
Materials 112.28 112.28
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 1582.60 1582.60
Taxes
Profit 507.94 507.94

Sheet Billing, Holiday Lighting, Takedown

Installation and Removal - Swagging Canopy Lights takedown, 30.89
Holiday Lighting Install
Total 30.89 30.89
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 23.79 23.79
Taxes
Profit 7.10 7.10

Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
Holiday Lighting Install 2240.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 1119.665

Edit - Landscaping_Software