Render Billing as PDF, Schedule of Values

Sheet Billing

Old re-used material in use, billing sheet will need to be computed manually.

Irrigation
Total 5835 5835
Materials 623.59 623.59
Subcontractors 0 0
Other/Delivery 575.00 575.00
Equipment
Labor 2844.00 2844.00
MOB 450.00 450.00
Taxes
Profit 1342.41 1342.41





Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
Irrigation 5835.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 2917.265