Render Billing as PDF, Schedule of Values
| Landscape | ||
| Total | 10953 | 10953 |
| Materials | 511.75 | 511.75 |
| Subcontractors | 4604.00 | 4604.00 |
| Other/Delivery | 600.00 | 600.00 |
| Equipment | ||
| Labor | 1807.50 | 1807.50 |
| MOB | 450.00 | 450.00 |
| Taxes | ||
| Profit | 2519.35 | 2519.35 |
| Project Scope | Contract | Completed | % Complete | + Add Day | |
|---|---|---|---|---|---|
| Landscape | 10953.00 | 0 % | 0.00 | ||
|
|||||
Total Project Completion: 0 %
Helper: 50% down is: 5476.395