Materials Sheet

NOTE: You have to reload this page before the materials sheet will update, hit F5.

Category Units Amount Cost To Buy List Total Purchased, Units Total Purchased, Dollar Amount









Holiday Lighting Labor Breakdown Area, With Crew Size , Install

Raw Install Labor, 155.00 Hours
Miscellaneous, Holiday Lighting, 0.00 Hours
MOB, 0.00 Hours
Total
Productive Labor Hours 310.0000 310.0000
GC Labor Hours 155.00 0
Crew MOB Hours 0 0.00
MOB Labor Hours 0.00 0.0000
Crew Labor Hours 77.5 155.00



Holiday Lighting Labor Breakdown Area, With Crew Size , Takedown

Raw Takedown Labor, 64.00 Hours
Total
Productive Labor Hours 128.0000 128.0000
GC Labor Hours 64.00 0
Crew MOB Hours 0 0.00
MOB Labor Hours 0.00 0.0000
Crew Labor Hours 32 64.00






No MOB reference




Holiday Lighting Labor Breakdown Area , Install

Raw Install Labor, 155.00 Hours
Miscellaneous, Holiday Lighting, 0.00 Hours
MOB, 0.00 Hours
Total
Productive Labor Hours 155.00 155.00
GC Labor Hours 155.00 0
Crew MOB Hours 0 0.00
MOB Labor Hours 0 0.00
Crew Labor Hours 155.00 155.00



Holiday Lighting Labor Breakdown Area , Takedown

Raw Takedown Labor, 64.00 Hours
Total
Productive Labor Hours 64.00 64.00
GC Labor Hours 64.00 0
Crew MOB Hours 0 0.00
MOB Labor Hours 0 0.00
Crew Labor Hours 64.00 64.00
Edit - Landscaping_Software

misc