Materials Sheet

NOTE: You have to reload this page before the materials sheet will update, hit F5.

Category Units Amount Cost To Buy List Total Purchased, Units Total Purchased, Dollar Amount
Sod SQFT 4768.00 $ 1293.33 Sod(2384.00), Pallet(2384.00), 0 0 See Invoice List->
Irrigation Zones ZONE 10.00 $ 3220.00 # of zones(10.00), 0 0 See Invoice List->
Fabric SQFT 4707.00 $ 341.26 Fabric(1577.00), Fabric(3130.00), 0 0 See Invoice List->
Edging FT 497.00 $ 1008.00 Edging(126.00), sticks(18.00), Edging(188.00), sticks(27.00), Edging(120.00), sticks(18.00), 0 0 See Invoice List->
1-1/2" Rock TONS 36.00 $ 2310.00 1-1/2" Local River Rock(36.00), 0 0 See Invoice List->
Topsoil TONS 33.00 $ 2100.00 Top Soil(33.00), 0 0 See Invoice List->
Demo SQFT 7500.00 $ 2000.00 Demo Sod(7500.00), 0 0 See Invoice List->
Tilling SQFT 2384.00 $ 0.00 Roto-tilling SF(2384.00), 0 0 See Invoice List->
Grading SQFT 2384.00 $ 0.00 Finish Grading SF(2384.00), 0 0 See Invoice List->
Compost TON 8.00 $ 400.00 Compost(8.00), 0 0 See Invoice List->
Concrete 339.00 $ 4994.00 Concrete,Grey Broom(338.00), Concrete,Boom Pump(1.00), 0 0 See Invoice List->
2" Tree 4.00 $ 1700.00 Tree 2"(4.00), 0 0 See Invoice List->
5 Gallon Shrub 12.00 $ 540.00 Shrub 5 gal(12.00), 0 0 See Invoice List->
1 Gallon 57.00 $ 1026.00 Perennial 1 gal(57.00), 0 0 See Invoice List->
3/8" Rock Ton 25.00 $ 2163.75 3/8" Gray Granite Chip(25.00), 0 0 See Invoice List->


Misc Items Needed:

Item Description Amount Needed Total Purchased, Units Total Purchased, Dollar Amount

3'x6'x2' Stock Tanks Tarter Agri Supply

11.00 0 0 See Invoice List->

8' stock tank Tractor Supply

1.00 0 0 See Invoice List->




Sod Irrigation Zones Fabric Edging 1-1/2" Rock Topsoil Demo Tilling Grading Compost Concrete 2" Tree 5 Gallon Shrub 1 Gallon MOB 3/8" Rock Total
Productive Labor Hours 12.0000 75.0000 15.0000 21.0000 36.0000 27.0000 45.0000 6.0000 6.0000 6.0000 0.00 9.0000 5.7600 13.6800 0.00 27.0000 304.4400
GC Labor Hours 0 0 0 0 0 0 0 0 0 0 8.00 0 0 0 0 0 8.00
MOB Labor Hours 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.0000 0.00 54.0000
Crew Labor Hours 4.00 25.00 5.00 7.00 12.00 9.00 15.00 2.00 2.00 2.00 0 3.00 1.92 4.56 0 9.00 101.48
Crew MOB Hours 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18.00 0 18.00
Edit - Landscaping_Software demo
mob
sod
tilling
grading
compost
sod
mob
edging
edging
3/8" rock
fabric
mob
edging
edging
miscellaneous
miscellaneous
topsoil
1-1/2" rock
fabric
mob
edging
edging
concrete
concrete
2" tree
plants
mob
5 gallon shrub
1 gallon
irrigation zones
mob