Materials Sheet

NOTE: You have to reload this page before the materials sheet will update, hit F5.

Category Units Amount Cost To Buy List Total Purchased, Units Total Purchased, Dollar Amount
Fabric SQFT 48.00 $ 3.48 Fabric(48.00), 0 0 See Invoice List->
1-1/2" Rock TONS 25.00 $ 210.00 1-1/2" Local River Rock(12.00), 1-1/2" Local River Rock(12.00), 1-1/2" Local River Rock(1.00), 0 0 See Invoice List->
Wall TONS 48.00 $ 804.00 Wall Blocks(24.00), Wall Blocks(24.00), 0 0 See Invoice List->
Cap TONS 24.00 $ 204.00 Caps(12.00), Caps(12.00), 0 0 See Invoice List->
Demo SQFT 48.00 $ 250.00 Demo Rock(48.00), 0 0 See Invoice List->
Steppers 1.00 $ 35.00 2' by 2' Steppers(1.00), 0 0 See Invoice List->


Misc Items Needed:

Item Description Amount Needed Total Purchased, Units Total Purchased, Dollar Amount

sand

1.00 0 0 See Invoice List->




Fabric 1-1/2" Rock Wall Cap Demo MOB Steppers Total
Productive Labor Hours 3.0000 3.0000 18.0000 12.0000 3.0000 0.00 3.0000 42.0000
GC Labor Hours 0 0 0 0 0 0 0 0
MOB Labor Hours 0.00 0.00 0.00 0.00 0.00 10.8000 0.00 10.8000
Crew Labor Hours 1.00 1.00 6.00 4.00 1.00 0 1.00 14.00
Crew MOB Hours 0 0 0 0 0 3.60 0 3.60
Edit - Landscaping_Software demo
mob
wall calculation
wall
cap
roadbase
1-1/2" rock
sand
wall calculation
wall
cap
roadbase
1-1/2" rock
sand
mob
steppers
fabric
1-1/2" rock
miscellaneous