Materials Sheet

NOTE: You have to reload this page before the materials sheet will update, hit F5.

Category Units Amount Cost To Buy List Total Purchased, Units Total Purchased, Dollar Amount
Miscellaneous 24548.00 $ 27125.00 Miscellaneous(0.00), Miscellaneous(3.00), Miscellaneous(24500.00), Miscellaneous(45.00), 0 0 See Invoice List->


Misc Items Needed:

Item Description Amount Needed Total Purchased, Units Total Purchased, Dollar Amount

2 Wire Installation Labor

0.00 0 0 See Invoice List->

Trencher

3.00 0 0 See Invoice List->

2 Wire Materials

24500.00 0 0 See Invoice List->

Bore

45.00 0 0 See Invoice List->




Miscellaneous MOB Total
Productive Labor Hours 300.0000 0.00 300.0000
GC Labor Hours 0 0 0
MOB Labor Hours 0.00 45.0000 45.0000
Crew Labor Hours 100.00 0 100.00
Crew MOB Hours 0 15.00 15.00
Edit - Landscaping_Software miscellaneous
mob
miscellaneous
miscellaneous
mob
miscellaneous